Engineering :: Industrial Engineering


  In case the probability factor is zero, it can be concluded that
[A]. the project is bound to fail[B]. the chances of completion of the project are 100%
[C]. the chances of completion of the project are 50%[D]. the chances of completion of the project are less than 50%.

Answer: Option C