Which of the following statement regarding PERT is incorrect?
|
[A]. |
It establishes the sequence and the relationship between significant programmes events | [B]. |
It is statistical technique which makes decisions
|
[C]. |
It points out slippages before the fact happens and its impact on others | [D]. |
It helps to formulate new schedules when the existing schedule cannot be met. |
|
|
|
|