  In voids method of determining the quantity of cement paste, it is assumed that the
[A]. voids in the coarse aggregate are filled by the fine aggregates[B]. volume of fine aggregates required for 1 m3 of coarse aggregate is equal to total voids in coarse aggregate plus 10% aggregate extra to allow for additional voids created by wedging action
[C]. volume of cement paste required for 1 m3 of coarse aggregate is equal to total volum of voids in the fine aggregate plus 15% aggregate extra to allow for additional voids created be wedging action[D]. all of the above

Answer: Option D